Ash Bridge Beam Installation 4th/5th May
Over the weekend on the 4th and 5th May there may be some local travel distruption if you are travelling to us via Ash level crossing.
Due to the installation of the new bridge beams on the 4th & 5th of May, there will be no trains operating between 2am Saturday and 4am Monday. We advise anyone travelling by train to us over the weekend to check the National Rail website first.
If you are travelling to us by road, we advise using Ash Hill Road to reach the dealership.
Activities on bridge site will be taking place in shifts throughout the weekend. There may be a brief lull during shift handovers, but work will be continuous.
Shift times:
Friday 8am to 6pm (as normal)
Friday 6pm to Saturday 6am
Saturday 6am to 6pm
Saturday 6pm to Sunday 6am
Sunday 6am to 6pm
Sunday 6pm to Monday 6am
The new beams and all equipment will arrive on site ahead of the weekend. There are approximately 19 beams which are being delivered mostly in pairs. The beams are 29m in length and will need to be guided into the site, so please be aware that there may be a brief delay to local journeys while the vehicles are guided through the gate.
The beams will travel via Ash Church Road and through the closed section of Foreman Road to the site entrance.
Further information
Please check the Guildford Borough Council website for up-to-date information (www.guildford.gov.uk/ashroadbridge).